BAS-506 Visual Aid Library

Figure-use rule

Each figure is an orientation and reasoning aid, not a project drawing. Learners must pair it with the current sequence, point list, wiring/piping documents, manufacturer instructions, and as-found evidence.

Figure 1 — Protocol mental model, layers, semantics, and demarcation critical

Normal-rule anchor

A protocol name does not define cable, routing, data meaning, writable authority, or physical result; each layer and contract must be proved.

Case overlay

A temperature reaches a supervisor through a legacy controller, serial gateway, IP network, and BACnet object, but no one owns the scale conversion.

Calculation/evidence callout: Count boundaries and dependencies, map addresses and transforms, and calculate end-to-end update and command-to-proof time.

Figure 2 — BACnet objects, properties, services, priorities, and conformance evidence critical

Normal-rule anchor

Object presence does not guarantee optional properties, services, writable behavior, units, priority support, or conformance; verify product claims and observed behavior.

Case overlay

A tool reads Present_Value but the object is out of service, units are wrong, and a write at priority 8 never reaches the equipment.

Calculation/evidence callout: Reconcile object and property coverage, active priorities, COV/timing, status, and command-to-proof response.

Figure 3 — BACnet/IP, routing, BBMD/FDR, and BACnet/SC critical

Normal-rule anchor

BACnet/IP, BACnet/SC, and IT network reachability are related but distinct; allowed traffic must be explicit and application behavior must be proved.

Case overlay

Devices discover locally but not across subnets, a foreign-device entry expires, and a proposed BACnet/SC hub has no certificate lifecycle owner.

Calculation/evidence callout: Calculate subnet and route coverage, BDT/FDR entries and TTL, packet/latency behavior, certificate lead time, and failure-domain impact.

Figure 4 — BACnet MS/TP and RS-485 token engineering critical

Normal-rule anchor

The token cannot fix the wire; screen discovery never replaces approved cable/topology, polarity, reference, termination, loading, grounding, and physical inspection.

Case overlay

A trunk has long stubs, mixed baud, duplicate MAC, missing end termination, and one device that appears only after power cycling.

Calculation/evidence callout: Calculate segment/device loading, token rotation estimate, baud-related transfer time, error concentration, and before/after response.

Figure 5 — Modbus data model, registers, functions, encoding, and polling critical

Normal-rule anchor

A plausible number is not valid evidence until the complete register contract and physical/process comparison are proved.

Case overlay

A meter value is 65,536 times too large, two devices share a serial address, and the gateway retries an unsupported function continuously.

Calculation/evidence callout: Convert addresses and raw values, test endian combinations, calculate poll-cycle/load and timeout/retry behavior, and compare engineering plausibility.

Figure 6 — LonWorks/LonTalk variables, binding, domains, and diagnosis critical

Normal-rule anchor

LonWorks connections behave like virtual wires; replacing or resetting a node without preserving identity, bindings, domain, configuration, and application can disconnect the system.

Case overlay

A replacement node powers up but its output network variables no longer reach three bound controllers.

Calculation/evidence callout: Reconcile node and domain identity, binding counts, update/heartbeat timing, SNVT units/scaling, channel load, and missing-variable coverage.

Figure 7 — Proprietary legacy systems: PUP, N2, Teletrol, and documentation-first support critical

Normal-rule anchor

Legacy experience is not permission to experiment; preserve rare documentation, tools, licensing, media, backups, cables, and known-good hardware while protecting customer data.

Case overlay

A Teletrol controller serves occupied equipment, its last backup is unknown, and a replacement gateway claims generic serial support without a verified point contract.

Calculation/evidence callout: Count assets and unsupported dependencies, score documentation/backup coverage, calculate polling and outage risk, and estimate migration verification effort.

Figure 8 — Gateways, transforms, timing, quality, command, and fallback critical

Normal-rule anchor

A gateway is an application with hidden state and blast radius; every transform and failure mode requires source, destination, ownership, test, and rollback.

Case overlay

A gateway continues serving cached normal values after its source bus fails and accepts writes without returning equipment proof.

Calculation/evidence callout: Calculate end-to-end latency, cache/stale thresholds, poll/write load, scale and enum transforms, command/proof timeout, and affected-point blast radius.

Figure 9 — Retrofit, coexistence, migration, cutover, cybersecurity, and life safety critical

Normal-rule anchor

Do not modernize by erasing the old truth; baseline, shadow comparison, owner authority, safety/critical interfaces, support window, backup, abort, and rollback precede cutover.

Case overlay

A hospital wing depends on a legacy interface that also reports smoke-control status, and the proposed gateway replacement changes network behavior.

Calculation/evidence callout: Calculate point and mode coverage, parallel comparison error, outage and rollback time, recovery objective, risk/exception counts, and acceptance pass rate.

Figure 10 — Integration commissioning, fault isolation, recovery, as-builts, and defense critical

Normal-rule anchor

Integration is complete only when required reads/writes, quality, timing, alarms/trends/schedules, physical response, failure/fallback, recovery, security, as-builts, and ownership all pass.

Case overlay

A mixed-protocol lab passes normal reads but fails after gateway restart and leaves one command active at an undocumented priority.

Calculation/evidence callout: Reconcile requirements/tests/issues/retests, calculate availability/latency/RPO/RTO, account for every target and temporary state, and quantify unresolved risk.