BAS-311 Evidence Workbook
Professional evidence workbook
Complete this while working the corresponding online lab. Entries save only in this browser until exported or printed. Do not enter live credentials, protected customer information, or uncontrolled personal data.
Terminal equipment recognition: VAV, FPB, FCU
Required artifact: equipment identity, normal modes, expected point signatures
| Identity, source, mode, authority | |
|---|---|
| Hazards, impacts, prohibited actions, stop criteria | |
| Expected normal and acceptance basis | |
| As-found evidence and timestamps | |
| Calculations with units and reasonableness | |
| Hypotheses, contradictions, discriminating test | |
| Action, expected result, abort/rollback | |
| Result, changed case, restoration, as-left | |
| Open risk, owner, due date, defense |
VVT, measured-airflow hybrid VVT, and VAV comparison
Required artifact: single-source constraints, airflow/reference behavior, relief/bypass strategy
| Identity, source, mode, authority | |
|---|---|
| Hazards, impacts, prohibited actions, stop criteria | |
| Expected normal and acceptance basis | |
| As-found evidence and timestamps | |
| Calculations with units and reasonableness | |
| Hypotheses, contradictions, discriminating test | |
| Action, expected result, abort/rollback | |
| Result, changed case, restoration, as-left | |
| Open risk, owner, due date, defense |
RTU/SZVAV/economizer sequence
Required artifact: staging/timers, fan/ventilation, integrated economizer, proof/failure
| Identity, source, mode, authority | |
|---|---|
| Hazards, impacts, prohibited actions, stop criteria | |
| Expected normal and acceptance basis | |
| As-found evidence and timestamps | |
| Calculations with units and reasonableness | |
| Hypotheses, contradictions, discriminating test | |
| Action, expected result, abort/rollback | |
| Result, changed case, restoration, as-left | |
| Open risk, owner, due date, defense |
VAV AHU simple-to-G36 progression
Required artifact: SAT/static/min-OA/reset request evidence and fallback
| Identity, source, mode, authority | |
|---|---|
| Hazards, impacts, prohibited actions, stop criteria | |
| Expected normal and acceptance basis | |
| As-found evidence and timestamps | |
| Calculations with units and reasonableness | |
| Hypotheses, contradictions, discriminating test | |
| Action, expected result, abort/rollback | |
| Result, changed case, restoration, as-left | |
| Open risk, owner, due date, defense |
Boiler/hot-water and pump reset/staging
Required artifact: load/temperature/valve/pump evidence, lead-lag and failure response
| Identity, source, mode, authority | |
|---|---|
| Hazards, impacts, prohibited actions, stop criteria | |
| Expected normal and acceptance basis | |
| As-found evidence and timestamps | |
| Calculations with units and reasonableness | |
| Hypotheses, contradictions, discriminating test | |
| Action, expected result, abort/rollback | |
| Result, changed case, restoration, as-left | |
| Open risk, owner, due date, defense |
Chiller/tower/pump sequence recognition
Required artifact: load/flow/ΔT/lift/staging/minimum-flow evidence
| Identity, source, mode, authority | |
|---|---|
| Hazards, impacts, prohibited actions, stop criteria | |
| Expected normal and acceptance basis | |
| As-found evidence and timestamps | |
| Calculations with units and reasonableness | |
| Hypotheses, contradictions, discriminating test | |
| Action, expected result, abort/rollback | |
| Result, changed case, restoration, as-left | |
| Open risk, owner, due date, defense |
VRF/heat-recovery/DOAS integration boundary
Required artifact: BAS-owned versus OEM-owned points, ventilation path, alarm/fallback
| Identity, source, mode, authority | |
|---|---|
| Hazards, impacts, prohibited actions, stop criteria | |
| Expected normal and acceptance basis | |
| As-found evidence and timestamps | |
| Calculations with units and reasonableness | |
| Hypotheses, contradictions, discriminating test | |
| Action, expected result, abort/rollback | |
| Result, changed case, restoration, as-left | |
| Open risk, owner, due date, defense |
Twelve-system recognition and two full traces
Required artifact: sequence identity, efficacy claim, failure mode, professional defense
| Identity, source, mode, authority | |
|---|---|
| Hazards, impacts, prohibited actions, stop criteria | |
| Expected normal and acceptance basis | |
| As-found evidence and timestamps | |
| Calculations with units and reasonableness | |
| Hypotheses, contradictions, discriminating test | |
| Action, expected result, abort/rollback | |
| Result, changed case, restoration, as-left | |
| Open risk, owner, due date, defense |